Commercial Office Renovation in Lagos

A 5-Week Project Case Study

Commercial Renovation · Office Fit-Out · Design & Project Management · Lagos, Nigeria

Commercial Renovation Office 04 1

A Better-Planned Office. Delivered in Five Weeks.

OurHomeFixer Limited undertook the renovation of a commercial office space to accommodate additional offices, a reception area and restroom facilities. The project required careful space planning, architectural design, cost estimation and coordinated construction to meet the client’s operational requirements.

The project was completed in five weeks against an original seven-week programme, demonstrating the value of clear planning and coordinated execution on this particular project.

Planning a commercial renovation or office fit-out? Let’s discuss your requirements.

Project Overview

Office Renovation in Lagos: A Commercial Renovation Case Study
Commercial Office Renovation in Lagos: A 5-Week Project Case Study

The Challenge

The client needed to adapt a new office space to meet the organisation’s operational requirements. The proposed layout needed to accommodate additional office areas, a reception space and restroom facilities while creating a professional working environment.

The project also required a clear plan before construction began, so that the scope, proposed layout, and cost could be reviewed before the client committed to the works.

Our Solution: Plan Before Construction

We approached the project through a structured process.

1. Requirements and space planning

We reviewed the client’s needs and considered how the existing space could accommodate the required facilities.

2. Architectural design

Several design options were considered. The preferred option was selected and refined through minor adjustments before proceeding.

3. Cost estimation and approval

After the design was finalised, a cost estimate was prepared within three working days. The client reviewed the proposal before approving the project.

4. Construction and coordination

Construction proceeded based on the approved design and project requirements, providing a defined reference for the work to be carried out.

5. Finishing and completion

The works focused on creating the required office areas, reception and restroom facilities, with attention to the completed space’s appearance and functionality.

Modern Corporate Lobby with Turnstiles
Commercial Office Renovation in Lagos A 5-Week Project Case Study
Office Renovation in Lagos: A Commercial Renovation Case Study

Project Programme: Five Weeks Instead of Seven

The original programme allowed seven weeks for completion. The project was completed in five weeks, two weeks earlier than originally scheduled.

This is a result from this specific project, not a guarantee that every commercial renovation can be completed within five weeks. Actual programmes depend on the scope, existing conditions, specifications, procurement, approvals and site constraints.

What This Project Demonstrates

  • Planning before execution: Design decisions were considered before construction began.

  • Cost visibility: The client received a cost estimate before approving the project.

  • Programme management: The work was completed within five weeks against the original seven-week programme.

  • Coordinated delivery: The project progressed from requirements and design through construction and finishing.

Commercial Renovation Office 17 1
Commercial Renovation Office 12 1

Our Five-Step Project Delivery Process

  1. Consultation & Site Inspection

  2. Bill of Quantities / Cost Estimate / Quotation

  3. Technical Drawings / Design & Visualisation

  4. Precision Construction & Management

  5. Quality Audit & Turnkey Handover

OURHOMEFIXER LIMITED NEW LOGO
Administative Hub 1

Building Something Exceptional?

Stay informed with expert construction insights, completed project showcases, renovation ideas, and company updates from OurHomeFixer.

We don’t spam! Read our privacy policy for more info.